Underwater Propeller Change, USS Enterprise, CVN-65

New Propeller Installed
The installation of the new propeller was
relatively straightforward. After arrival and visual inspection, the 34 ton,
21-foot replacement propeller was lifted from the flatbed truck and placed on
the pier using the 100 ton floating crane. A lifting eye had been installed in
the propeller hub. This would allow the dive team to rotate the propeller 90
degrees on its axis before lowering it into the water alongside the barge. This
was accomplished by utilizing the 50-ton chain hoist. Before the propeller was
lowered into the water alongside the barge, all gland ring studs and dunce cap
studs were installed and torqued. The propeller and the attached 50-ton chain
hoist were then lowered and secured to the barge is balance beam. The barge was
then repositioned alongside the Enterprise at Frame 228 and the divers
installed the O-Ring and gland ring on the shaft.
The propeller was rigged from the barge's
balance beam under the ship to the aft 50-ton chain hoist in a yard and stayed
arrangement. Using a yard and stay arrangement with the foreword and the aft
50-ton chain hoists, the propeller was positioned on to the shaft and advanced
up the taper. A 6-ton chain fall attached to the strut assisted in advancing
the propeller up the taper to within one-half inch of its final
seat.
The pilgrim nut with its attached wire sling
and snatch block was yard and stayed into place and screwed on to the shaft
until it was hard against the propeller hub. It was pressurized to 14,000 PSI,
retightened and repressurized to 16,000 PSI - thus seating the propeller home.
The pilgrim nut and the 3, 50-ton chain hoists were then removed. The boss nut,
already installed in its speed wrench, was yard and stayed from alongside the
barge to the after propeller lifting hall fitting. It was then yard and stayed
into place on the threads by fore and aft a rip hoists. The nut was advanced by
wrapping and pulling wire about the nut circumference. Once into place it was
tightened with the nut wrench. The lock pin hole was lined up, the pin
installed and the wrench was then removed.
The dunce cap was rigged under the ship
using the after grip hoist wire, it's O-ring installed and rigged into position
against the propeller hub, using the forward grip hoist wire. The dunce caps
stud nuts were installed, torqued to 575 foot pounds, and the cover plates were
screwed back into place. The forward gland rain nuts were installed and torqued
to 105 foot pounds. The propeller and dunce cap were flushed with preservative
until no water was present. The screw cavities were then filled with
preservative. Vent and fill plugs were installed. The dunce cap was pressurized
to 25 PSI, checked for leaks, then filled with preservative and plugged. The
dive team had successfully completed the propeller change on the waterborne
USS Enterprise.
WebMaster Bruce
|